Project Name: Well No. 20
Location: 1300 West El Segundo Blvd., Compton, CA 90222
Owner: City of Compton
Description of project and scope of work performed: ACSE designed and developed programming, built UL-508a control panel, programmed Allen-Bradley PLCs to monitor and control the well site pumps and booster pumps, and tank levels and all associated instruments.
_____________________________________________________________________________________
Project Name: San Joaquin Marsh Outlet Pipe Valve Replacement
Owner: Irvine Ranch Water District
Description of project and scope of work performed: ACSE designed and developed programming, built UL-508a control panel, programmed Modicon PLCs .
_____________________________________________________________________________________
Project Name: Recycled Water System Expansion
Location: 380 Avenida Pico, San Clemente, CA 92672
Owner: City of San Clemente
Description of project and scope of work performed: ACSE designed, procured and manufactured the PLC panel in accordance with the UL508a standards, programmed the Allen Bradley PLC (Compact Logix 1769 series), set up the communication with SCADA (Wonderware), and created new SCADA objects(Wonderware) for the newly installed equipment. Total No. of I/Os: 400 DIs, 148 DOs, 80 AIs and 32 AOs.
Project Name: Well No. 20 & Treatment Works
Location: Moorpark, CA
Owner: County of Ventura
Description of project and scope of work performed: Designed and manufactured control panels and selected field instruments, programmed the PLC and HMIs, using Pressure Transmitters, Pressure Switches, Level Transmitters
(Allen Bradley, Control Logix PLC 1756 series).
ACSE Current Projects
Our Testimonials:
“As Sr. estimator and project manager, I have worked closely with ACSE on numerous projects. I have found their performance and quality of work to be exceptional and above that of their competitors. As a sub-contractor, they have proven to be one of the best for consistently maintaining a clean and safe working environment.”
Kavous Emami
“ACSE was a delight to work with. Their industry experience and ability to produce a complaint design under strict time constraints has been invaluable to the projects. I have found their work standards and attitude to be exemplary. They ensure the highest quality is always achieved to meet the project’s requirements.”
Kevin Nguyen,